Description
RENO BOTTOMS HREP, STAGE 2, ICE HAUL SLOUGHThis contract is for the construction of island enhancement features and Ice Haul closure structure in the backwater area of Pool 9 of Reno Bottoms of the Mississippi River. The projects purpose is the restoration and protection of diverse bottomland forest habitat. Structures must be constructed with fine fill materials from habitat dredging and granular material from offsite stockpiles. Provide riprap and place it along the shore to protect the island in selected areas.