This project will rehabilitate Hurricane Ridge water system by replacing all galvanized and A.C. piping with HDPE piping, sized for system demands. This project will also rehabilitate the 100,000-gallon in-ground concrete reservoir by blasting and coating both interior and top of tank, and reconfiguring valves and pump control system. Remote monitoring of water system parameters will be added to a temporary utility building, and obsolete components of the surface water system will be demolished.
Planning details
- Estimated value
- $2M - $4.9M
- Contract type
- To Be Determined
Classifications
- NAICS237110
- PSC237110