During the February and April of 2020, a series of heavy rain events caused significant roadway damages within the Cherokee National Forest. The damaged roadways prevent roadway public access into various points of the Cherokee National Forest. Damages include large landslides, roadway and shoulder washouts, clogged or damaged culverts, and other miscellaneous work. Project TN ERFO FS CHRKE804 2020-2(5) will repair storm and flood damage on Citico Creek Road (FS 35-1) and Spring Creek Road (FS 27). This project consists of grading, roadway resurfacing, drain dip construction, replacement of drainage culverts, construction of Aquatic Organism Passage (AOP) structures, drainage culvert cleaning, ditch reconditioning, slope stabilization repairs, and other miscellaneous work.
Planning details
- Estimated value
- $10M - $19M
- Contract type
- Firm Fixed Price
Classifications
- NAICS237310
- PSC237310