USCGC ALEX HALEY Switchboard Replacement
- Est. solicitation
- May 20, 2027
- Date posted
- Sep 16, 2026
- Source
- Open forecast
Description
The 282-FT USCGC ALEX HALEY (WMEC-39) Ship Service Switchboards are no longer supportable and require replacement. This project entails the replacement of the ship's service switchboards through a comprehensive three-phase process covering design, fabrication, and installation support. The new 450 VAC, three-phase switchboard must adhere to strict dimensional constraints, with a maximum size of 192 inches in length, 25.25 inches in depth, and 81 inches in height, and must be built to UL 891 and IEEE 45 standards. Designed for a marine environment, it will consist of four separable sections to facilitate rigging and installation and must withstand up to 45° rolls and 10° pitch. Additionally, the vendor will be required to perform critical electrical system analyses, including studies on fault currents, protective device coordination, arc flash, and failure modes.
Planning details
- Estimated value
- $2M to $5M
- Award quarter
- Q1 2028
- Est. solicitation date
- May 20, 2027
- Anticipated award
- Dec 6, 2027
- Contract vehicle
- PO (FAR Subpart 13.5)
- Contract type
- Firm Fixed Price
- Competition
- New Requirement, No Contract
- Status
- NEW
- Fiscal year
- 2028
- Period of performance
- Dec 6, 2027 – Dec 5, 2028