Y--North Gunnison Substation 115kV Switch Install
ENERGY, DEPARTMENT OF
- Response deadline
- Jul 6, 2026 Closed
- Date posted
- Jun 12, 2026
- Source
- Open notice
Description
North Gunnison 115-kV Switch Installation to add a 115kV Disconnect Switch to the bus work to provide flexible operation to feed the North Gunnison loads and allow WAPA to maintain all the electrical substation equipment. a. Provide demolition and site development. b. Remove and dispose of existing pedestals, rigid bus, insulators, and concrete foundations. c. Furnish and install 115kV disconnect switch, structural steel, foundations, and associated equipment.
Classifications
Documents (1)
- attachmentNot yet available
Contacts
- Pratt, John W.jpratt@wapa.gov720-962-7166