Stegall Substation Stage 07 Phase 01

ENERGY, DEPARTMENT OF
Response deadline
Aug 10, 2026
Due in 24 days
Date posted
Jun 29, 2026

Description

The Stegall Substation Stage 07 Phase 01 Project (Equipment Replacements and Upgrades) replaces end of life equipment and installs a new control building. Replaced equipment shall include the 1960’s era control building, 30+ disconnect switches, problematic brown glass insulators, main bus reconductor and rating increase, 2-115kV oil circuit breakers, replace 1990’s vintage GE D20 RTU with three SEL RTACs, and add transfer bus dead end structure between 230kV east and west interconnect.