sc_scbo5h2z83iz3ef
Open
Backup Generator for Well
- Response deadline
- Oct 13, 2026 Due in 12 days
- Date posted
- Sep 10, 2026
- Source
- Open notice
Description
INSTALLATION OF ONE PERMANENT MOUNTED DIESEL GENERATOR AND SCADA SYSTEM WITH ALL ASSOCIATED ELECTRICAL MODIFICATIONS, CONCRETE PAD, MINOR SITE GRADING AND ALL OTHER RELATED WORK. TIME ALLOTED FOR THIS WORK IS 270 CONSECUTIVE CALENDAR DAYS FOR SUBSTANTIAL COMPLETION AND 300 DAYS FOR FINAL COMPLETION.
Documents
No documents posted for this opportunity.
Contacts
- emettehutto@gmail.com803-645-6420