nc_evp274-TM-5-26
Open
The Project consists generally of the following major items: • The complete removal and disposal of existing sidewalk ramps as identified by the City of Raleigh and replacement with upgraded ADA-co…
- Response deadline
- Jun 18, 2026 Closed
- Date posted
- May 18, 2026
- Source
- Open notice
Description
The Project consists generally of the following major items: • The complete removal and disposal of existing sidewalk ramps as identified by the City of Raleigh and replacement with upgraded ADA-compliant access ramps within the City areas under its jurisdiction • The removal and replacement of sidewalk panels, curb and gutter as identified by the City of Raleigh in accordance with project specifications • Resetting permanent and hinged bollards in place as specified in the contract • The restoration of all disturbed areas including backfilling, grading, seeding and mulching with NCDOT approved seed mixtures
Documents
No documents posted for this opportunity.