The Project consists generally of the following major items: 1. Remove and replace six packaged units and one split system for a total of 57 tons. 2. Clean existing ductwork on existing units. 3. P…

Response deadline
Sep 22, 2026
Due in 32 days
Date posted
Aug 21, 2026

Description

The Project consists generally of the following major items: 1. Remove and replace six packaged units and one split system for a total of 57 tons. 2. Clean existing ductwork on existing units. 3. Provide pre-construction and post-construction test and balance. 4. Provide new control system via new controllers and new jace. 5. Add Alternate #1: Replace RTU-1 air distribution for new VAV controls; complete with ductwork, terminals, etc. 6. Add Alternate #2: Replace two existing toilet exhaust fans.