nc_evp274-ES-FO-FY26-KeeterTrainingCenterWaterproofing
Open
Excavation and removal of the soil against the building elevation to waterproof the below grade structure, and to back fill with new soil. During the removal of soil, landscaping and utilities will…
- Response deadline
- May 21, 2026 Closed
- Date posted
- Apr 21, 2026
- Source
- Open notice
Description
Excavation and removal of the soil against the building elevation to waterproof the below grade structure, and to back fill with new soil. During the removal of soil, landscaping and utilities will need to be considered. An inspection of the building drainage system will reveal any roof leader or foundation drain damage or malfunction. The contractor is expected to repair and replace as needed. Additionally, the ramped walkway to the building’s entrance forms a border of the excavation area. This ramp will require temporary shoring to be provided by the contractor during the waterproofing excavation.
Documents
No documents posted for this opportunity.