il_bidbuy19-422DNR-MINES-B-4763
Open

DNR - OMM - CO2(Notice of Change Order) - Northwestern and Diamond No. 5 Mines AML1407

Response deadline
Jan 1, 2019
Closed
Date posted
—

Description

CHANGE ORDER NOTICE:CO#2: IDNR is giving notice of a change order.Contract change order is required to increase the contract in the amount of $77,829.00 for a new contract total of $450,908.10. This change order is a 20.9% increase to the current contract amount. These circumstances were unforeseeable at the time and germane to the original contract. Change order is in accordance with 720 ILCS 5/33E-9. (ref. original contract P-5765)

Classifications

Documents (1)

  • Notice of Change Order-CO2- Gibbs-Northwestern and Diamond No. 5 Mines- AML1407.docx
    text/html; charset=UTF-82 KB