il_bidbuy19-422DNR-MINES-B-4467
Open

DNR - OMM - CO2 - Demaree Highwall/Peabody Key - 1502

DNR - Natural Resources — MINESMINERALS422 - Office of Mines and Minerals · IL
Response deadline
Dec 14, 2018
Closed
Date posted

Description

CHANGE ORDER NOTICE:CO#2: IDNR is giving notice of a change order. The Agency requires change order as defined in 30 ILCS 500/1-15.12 and 720 ILCS 5/33E to increase the contract in the amount of $55,615.60 for a new contract total of $810,824.60. This change order is a 7.4% increase to the current contract amount. These circumstances were unforeseeable at the time and germane to the original contract.(ref. original contract: P-1608)

Classifications

Documents (1)

  • Notice of Change Order-CO2- OakHill-- Demaree Highwall-Peabody Key AML1502.docx
    text/html; charset=UTF-82 KB
    Download