CHANGE ORDER - cost increase of $12,320 DNR Moraine View Site House Renovation

DNR - Natural Resources — LNDMGMT422 - Office of Land Management · IL
Response deadline
Aug 9, 2019
Closed
Date posted

Description

Change order notice-increase cost by $12,320 to apply new sheathing on roof. Existing plywood decking is rotted. These circumstances were unforeseeable at the time and germane to the original contract. Change order is in accordance with 720 ILCS 5/33E-9. (ref. original contract - P-9547)