LETTING LOCATION: 1074 HWY. 90 Chipley POSTING DATES: 09/03/2026 and 09/17/2026 CONTRACT DAYS: 850 CONTRACT EXECUTION DAYS: 10 SPECIAL START DATE: N/A ACQUIS./FLEXIBLE START TIME: 30 Days Flexible The work under this District Contract consists of providing the labor, material, and equipment necessary to complete the landscaping project located at SR 8A (I-110) from east of Maxwell Street to SR 8 (I-10) in Escambia County. A total of 120 Contract days will be allowed for the installation period and 730 Contract days will be allowed for the establishment period. Contractor Experience in Landscaping (Form 850-070-09) is required to be submitted with bid. Counties: ESCAMBIA Highway: 4827 Eligibility: Eligible