Civic AI
Procurement intelligence
Federal contract award
THIS IS A EQUITABLE ADJUSTMENT FOR $87,784.52 FOR THE JENNINGS RANDOLPH WINDOW REPLACEMENT PROJECT RELATED TO 5 WEEKS OF EXTRA ON SITE TIME TO COMPLETE IN ELKINS, WV.
ARK CONSTRUCTION MANAGEMENT LLC · General Services Administration
- Value
- $2,702,689
- Start
- Aug 15, 2024
- End
- Nov 17, 2025
- Action date
- Apr 21, 2026
- PIID
- 47PD0224C0023
- Status
- completed
- NAICS
- 236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION
- Place of performance
- ELKINS, WV
- Award type
- DEFINITIVE CONTRACT
Description
THIS IS A EQUITABLE ADJUSTMENT FOR $87,784.52 FOR THE JENNINGS RANDOLPH WINDOW REPLACEMENT PROJECT RELATED TO 5 WEEKS OF EXTRA ON SITE TIME TO COMPLETE IN ELKINS, WV.