Civic AI
Procurement intelligence
Federal contract award
THE NO COST TIME EXTENSION MODIFICATION FOR THE AERIAL WALKWAY BRIDGE REPAIRS AND REPLACEMENT- CM SERVICES CONTRACT IS TO EXTEND THE POP COMPLETION DATE FROM 1/30/26 TO 4/29/26 AND TO EXTEND THE THE ULTIMATE ESTIMATED COMPLETION DATE FROM TO 6/29/26
AFG GROUP INC. · General Services Administration
- Value
- $216,000
- Start
- Oct 21, 2024
- End
- Apr 29, 2026
- Action date
- Feb 19, 2026
- PIID
- 47PC0224F0097
- Status
- completed
- NAICS
- 541330 · ENGINEERING SERVICES
- Place of performance
- ALBANY, NY
- Award type
- DELIVERY ORDER