THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NO COST CHANGE TO REMOVE THE EXISTING CULVERT AND REPLACE IT WITH A 20 FOOT LONG, 24 INCH DIAMETER CULVERT. ALSO TO REDUCE 12 BOULDERS AND 45.22 CYD OF CUT. EXTENSION OF THE PERIOD OF PERFORMANCE.

COOLEY & SONS EXCAVATING, INC. · Department of the Interior

Value
$283,524
Start
Aug 27, 2025
End
May 30, 2026
Action date
Jan 23, 2026
PIID
140L1725C0005
Status
completed
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION
Place of performance
ALAMOSA, CO
Award type
DEFINITIVE CONTRACT

Description

THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NO COST CHANGE TO REMOVE THE EXISTING CULVERT AND REPLACE IT WITH A 20 FOOT LONG, 24 INCH DIAMETER CULVERT. ALSO TO REDUCE 12 BOULDERS AND 45.22 CYD OF CUT. EXTENSION OF THE PERIOD OF PERFORMANCE.