P00002 - MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE THROUGH AUGUST 31ST, 2026 DUE TO DELAYS ON THE WEST CRYSTAL TO PROJECT PRECEDING THIS ONE. NTP NEVER ISSUED, THEREFORE POP AND CONTRACT TIME DID NOT BEGIN.
EPIC CONSTRUCTION & ENVIRONMENTAL INC. · Department of Agriculture
- Value
- $384,020
- Start
- Aug 12, 2024
- End
- Aug 31, 2026
- Action date
- Jan 23, 2026
- PIID
- 1240LT24F0031
- Status
- active
- NAICS
- 237310 · HIGHWAY, STREET, AND BRIDGE CONSTRUCTION
- Place of performance
- RED FEATHER LAKES, CO
- Award type
- DELIVERY ORDER
Description
P00002 - MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE THROUGH AUGUST 31ST, 2026 DUE TO DELAYS ON THE WEST CRYSTAL TO PROJECT PRECEDING THIS ONE. NTP NEVER ISSUED, THEREFORE POP AND CONTRACT TIME DID NOT BEGIN.